17Jul2018 Construction ProcessFinal Walk ThroughJuly 17, 2018 / by evonneDarren and I did our first final walk-through yesterday at the house, and we also signed all the escrow documents at the title company. The house is pRead More
9Jul2018 Construction ProcessWe Have Backsplash and Appliances!July 9, 2018 / by evonneThis past week, the contractors installed the backsplash in the kitchen. I have been going back and forth with this backsplash… somedays I am haRead More
24Jun2018 Construction ProcessCountertops + Hardware Fixtures InstalledJune 24, 2018 / by evonneA little more progress on the house this past week – all the countertops and hardware fixtures are installed. We chose quartz countertop for theRead More
17Jun2018 Construction ProcessLight Fixtures and Tile Floors Are InJune 17, 2018 / by evonneThis week at the house, the light fixtures and tile floors are in! I can’t believe that all the selections that we made at the Home Gallery lastRead More
10Jun2018 Construction ProcessCabinets & Interior Wall Paint CompletedJune 10, 2018 / by evonneDarren and I just got back from our 2-week trip to Hong Kong and when we checked on our house yesterday, the cabinets and interior wall paint are all Read More
20May2018 Construction ProcessThe Interior Drywall is Done!May 20, 2018 / by evonneThe interior drywall is done at the new house… there was a lot of progress since last week when we went to visit. The outside exterior walls areRead More
12May2018 Construction ProcessExterior Walls, Insulation + Electrical WiringMay 12, 2018 / by evonneThe exterior walls, insulation, and electrical wiring are already in place at the new house. A lot of progress has been made since we last saw it in ARead More
23Apr2018 Construction ProcessPlumbing and Star R Foam Insulations InstalledApril 23, 2018 / by evonneWe went to check on the house yesterday and the plumbing and Star R Foam wall insulations are installed. We were out of town for 3 weeks to visit famiRead More
14Apr2018 Construction ProcessFrame Walk CompletedApril 14, 2018 / by evonneWe did a frame walk with the construction manager 2 weeks ago right before we left for our family trip. The interior ducts and vents are in, and the pRead More
11Mar2018 Construction ProcessPorch Awning + Fire Sprinkler System Are InstalledMarch 11, 2018 / by evonneThe porch awning and the CPVC fire sprinkler system inside the house are installed. It’s been 20 days since we last checked on the house. We canRead More